Installed wet pipe sprinkler, standpipe, two dry fire protection systems, and replaced fire department valves
Grunau Location: Pennsylvania Office
Owner: University of Pittsburgh
Contractor: Burchick Construction Company
Engineer: Burt, Hill, Kosar, Rittleman Associates
Case Study: PA ~ Holland Hall at Univ of Pittsburgh Case Study
Completed: August 2003
Furnished standpipes and installed fire department valves, test and drain riser, 180 sprinklers, and 2-hour insulation
Grunau Location: Pennsylvania Office
Owner: Verizon, PA
Contractor: Jendoco Construction Company
Engineer: LLI Technologies, Inc.
Completed: June 2003
Installed 125 wet and dry sprinklers for the ground, first floor and balcony; tied into existing water supply of this historical landmark building within the University of Pittsburgh’s campus
Grunau Location: Pennsylvania Office
Owner: University of Pittsburgh
Contractor: Poerio, Inc.
Architect: WTW
Engineer: H.F. Lenz
Completed: September 2002
Installed wet sprinklers, water service for secondary supply, dry system, and diesel fire pump in Towers A, B, and C with acoustical ceilings and drywall
Grunau Location: Pennsylvania Office
Owner: University of Pittsburgh
Engineer: Burt, Hill, Kosar, Rittleman Associates
Completed: August 2002
Installed fire line, standpipes, 1,300 sprinkler heads, and electrical wiring of installed flow and tamper switches. Reprogrammed fire alarm panel.
Grunau Location: Pennsylvania Office
Owner: Carnegie Museum of Pittsburgh
Engineer: Eichleay Engineering, Inc.
Completed: August 2002
Installed dry pipe sprinkler system and dry standpipe system in parking garage of Magee Hospital
Grunau Location: Pennsylvania Office
Owner: Magee Women’s Hospital
Contractor: Turner Construction Company
Architect: Tsoi/Kobus Associates
Completed: March 2002
Installed 1000 gmp electric fire pump, wet and dry sprinklers
Grunau Location: Pennsylvania Office
Owner: University of Pittsburgh
Contractor: Pitt Center Partners
Architect: Apostoluo, Russer
Engineer: Brinjac Engineering
Completed: January 2001
Converted wet fire protection system to dry fire protection system. Installed a double-lock preaction system in a cooler/freezer and an Early Suppression, Fast Response (ESFR) wet system for dry storage
Grunau Location: Pennsylvania Office
Owner: Alliant Foodservice
Contractor: Environmental Structures
Completed: Ongoing